Northland DHB Hospital Redevelopment Private: Tumanako

Project Construction

Project Deadline
Development of Site Master Plan March 2008
Business Case submitted September 2008
Business Case approval April 2009
Procurement of principal consultants August 2009
Concept Design/Brief January 2010
Preliminary Design March 2010
Developed Design June 2010
Detailed Design August 2010
Tendering for main contractor June to September 2010
Construction commencement October 2010
Completion Late 2011